Rānui Generation Solar Farms
Twin Rivers - Kaitaia
The Twin Rivers Solar Farm is Rānui Generation's first, and northern most project in New Zealand. It has been designed with a nameplate capacity of approximately 30MWp and 24MWac grid connection .
Once commissioned, the solar farm will generate approximately 42GWh per annumn from the 34 hectare site.
Tenders for the project have now been awarded and construction is underway. Updates on the construction will be published on the website.
Three Streams - Kaponga
The Three Stream Solar Farm is located in Kaponga, Taranaki. It has been designed with a nameplate capacity of approximately 38MWp and 32MWac grid connection.
The solar farm area is 48ha, and once comissioned will generate approximately 53GWh per annum.
Resource consent for the construction, operation and maintenance of the project has now been granted approval non-notified from South Taranaki District Council.
We are now looking to commence the tender process for this project, construction for which is planned to commence Q2 2025. If you would like to register your companies interest, please contact us via info@ranuigen.co.nz. We are keen to hear from companies of all sizes, particulalry those based in region.
Skinner Road - Stratford
The Skinner Road Solar Farm is located in Stratford, Taranaki. Resource consent for this project was lodged with Stratford District Council in August 2023 and is currently being processed.
With a nameplate capacity of approximately 40MWp and 32MWac grid connection, the solar farm will generate approximately 55GWh per annumn from the 47 hectare site.
Tikokino - Central Hawkes Bay
The Tikokino Solar Farm is located in Central Hawkes Bay. This project is in early design stage.
The project is designed with a nameplate capacity of up to 55MWp and 43MWac grid connection, the solar farm will generate approximately 61GWh per annumn from the 57 hectare site.